Europe offshore wind build-out must triple to bring Paris goals within reach

Europe offshore wind build-out must triple to bring Paris goals within reach

To support the Paris Agreement’s goal of limiting temperature increase to 1.5°C, Europe will need a CO2-neutral electricity supply by 2045. A target we cannot meet unless we ramp up Europe’s offshore wind capacity, says Michiel Müller from consultancy Ecofys, a Navigant company.

The company’s energy experts calculated that the current offshore wind installation rate

They argue that an integrated North Sea Grid is the only way to achieve this growth at lowest possible cost while maximizing benefits to the environment.

To meet the goal agreed at the Paris climate change conference in December 2015, Europe will need a fully decarbonized electricity supply by 2045.

Renewables are essential to making this happen.

 

 

The joint energy team of Ecofys and Navigant have investigated Europe’s renewable generation resources and find that offshore wind from the North Seas region will be pivotal for realising a 100% decarbonised electricity supply in less than 30 years.

In their analysis, the experts looked specifically at the ten countries around the North Sea – France, Belgium, the Netherlands, Luxemburg, Germany, Denmark, Sweden, Norway, Ireland, and the United Kingdom – that cooperate in the EU-supported North Seas Countries Offshore Grid Initiative established in 2009.

Such growth in offshore wind cannot be realised through individual efforts—it is possible only through a new level of collaboration, coordination, and interconnectivity between the North Seas countries

To determine the required offshore capacity for the whole region, the team started with the 2045 electricity demand per country and assumed a complete phaseout of fossil-fueled electricity generation, as well as a started retirement of nuclear.

We assumed that current operational nuclear plants will be decommissioned and not replaced after their lifetime. Thus, the only nuclear plants around by 2045 will be new ones that are in an advanced planning stage today.

The Ecofys and Navigant consultants then determined the total available onshore generation capacity by means of several scenario studies and identified how much of the Paris-compatible electricity generation capacity can be met on land.

The countries’ joint onshore generation resources (wind, solar, bio, hydro, and remaining nuclear)could provide up to 55% of the required capacity.

This leaves 45% to be covered by offshore sources and translates into an  offshore wind target of approximately 230 GW for the North Seas countries. [ 180 GW of that capacity could be generated in the North Sea, and the remaining 50 GW in other seas like the Baltic and Irish Seas and the Atlantic.

With 13 GW installed currently, however, the region is far from the required total. To realise this growth, the offshore wind installation rate would have to triple from the current 3 GW/year to approximately 10 GW/year in 2030.

Fonte: Wind Europe

Source: Wind Europe

Long-term spatial planning

Such growth in offshore wind cannot be realised through individual efforts—it is possible only through a new level of collaboration, coordination, and interconnectivity between the North Seas countries.

In addition to its role as a natural habitat, the North Sea is intensely used as a place for fisheries, tourism, military zones, oil & gas infrastructure, and shipping, and therefore of vital importance to the region’s economy.

While there is sufficient space to develop the required offshore wind capacity (current estimates indicate that some 10% of the North Sea surface will be required for offshore wind, based on a wind farm intensity of 5-6MW/km2), a careful balance must be maintained, ensuring maximum benefit to the environment and cost-efficient development of both wind farms and associated infrastructure.

The analysis shows that Great Britain and Ireland have a need for import capacity of roughly 30 GW, while continental North Western Europe has a deficit of 25 GW

Harnessing and preserving the environment of the North Sea region requires constructive collaboration among all sectors. The potential offshore grid could support the marine biodiversity through new protected areas for wildlife and extended migratory corridors.

This requires a shared long-term view by all North Sea countries. A joint spatial planning strategy is needed to reflect changes in use (e.g., decommissioning of oil & gas) and ensure a cost-efficient utilization of the resource, aligned with offshore and onshore grid development and environmental protection.

50 GW-80 GW interconnector capacity required for grid balancing

Long-term planning will also have to go into securing the stability of such new infrastructure. With higher shares of renewable energy, the stability of the grid heavily depends on an increase in flexibility options.

A crucial enabler for a flexible power system is a well-developed network, or in the case of the North Sea offshore wind-dominated system, an infrastructure with increased levels of interconnectivity.

Based on a high level adequacy assessment, we determined the likely reliable capacity that would be available. Ecofys investigated peak demand situations for the three sub-systems around the North Sea: Great Britain and Ireland, continental Northwestern Europe, and the Nordics.

The team analysed how much wind power is available at minimum wind conditions with regard to climatic data and the geographical spread of wind parks.

Comparing the results with the available onshore resources, dispatchable generation and flexibility from demand and storage, they deducted the margin each of the three ‘sub-systems’ has. A negative margin shows a need to interconnect to regions with more resources.

With the phaseout of fossil-fueled electricity generation the dispatchable generation capacity drops from a level of 64% in today’s generation mix to approximately 25%

The analysis shows that Great Britain and Ireland have a need for import capacity of roughly 30 GW, while continental North Western Europe has a deficit of 25 GW. An overall level of 50 GW-80 GW of interconnection capacity will be required for the North Seas area.

Growth of interconnection capability requires a careful evaluation of the cost-benefit analysis approach. A new methodology to value grid stability could incentivize interconnector capacity.

Current planning practice often limits the level of offshore interconnections to save operational costs.

Source: RE-New Economy

Date: September 2017

Read the article


Tags assigned to this article:
climate changeCOP21 @enenergy policywind

Related Articles

Pope’s climate push at odds with U.S. Catholic oil investments

Pope Francis heartened environmentalists around the world in June when he urged immediate action to save the planet from the

Wind could supply fifth of world electricity by 2030

Wind power could supply as much as 20 percent of the world’s total electricity by 2030 due to dramatic cost

Scientists foresee losses as cities fight beach erosion

Beaches are facing off against a changing climate, and they’re losing ground. Literally. Waves, currents, storms and people all move